Flat Ridge Interconnect & Transmission Line
BP Alternative Energy NA, Inc.
INTERCONNECTING UTILITY:
Sunflower Utility
RMT'S ROLE:
- Engineering, procurement, and construction of 4.6 miles of 138 kV transmission line, 34.5/138 kV project substation, 138 kV five breaker radial bus interconnection switching substation
- Engineering of cap banks for substation
- Fiber optics communication and SCADA network
PROJECT HIGHLIGHTS:
- Provided SCADA and RTU equipment and programming to accommodate four different parties with different logic protocol
- Coordinated schedule with the client, who acted as the general contractor, and another onsite general contractor
- Supported the owner for installing owner-purchased material and working around the owner’s delayed delivery schedule
- Provided ongoing energy, environmental, and
economic benefits:
- Generates enough electricity to power approximately 30,000 homes annually
- Offsets the combustion of approximately 136,000 tons of coal per year, which reduces the equivalent of 180,000 tons of CO2 emissions to the atmosphere annually
- Provides income to local landowners through annual lease payments