Post Rock Wind Project
Wind Capital Group
INTERCONNECTING UTILITY:
WESTAR Energy
RMT'S ROLE:
- Engineering, procurement, and construction of the civil and electrical infrastructure
- Construction of 19.6 miles of access roads
- 31 miles of new 230 kV transmission line
- Crane paths and pads
- Spread-footer turbine foundations
- 24.6 miles of 34.5 kV underground collector system
- 34.5/230 kV power substation
- In-tower wiring
- Construction of two meteorological towers
- Mechanial turbine completion
- Tower erection
- Testing and inspections
- Full site restoration
PROJECT HIGHLIGHTS:
- Post Rock Wind is currently under construction and is scheduled for completion in July 2012
- Generates enough electricity to power over 70,000 homes annually
- Stimulated local businesses during development and construction with over $1.5 million in economic activity